Comic Con Liverpool Countdown 🦹

Open search Close search

Close menu

Everton FC

Everton Stadium ‘structurally complete’ as final terracing panel installed

2 months ago

Everton Stadium ‘structurally complete’ as final terracing panel installed
Credit: Everton Stadium

The final concrete terracing panel has been installed to complete the structural work within the bowl of Everton Stadium.

The final piece of the huge jigsaw was lowered into place in the east stand of Everton Stadium this week, ending 18-months of complex work since the first concrete terrace was positioned in August 2022.

And with all 1,988 double-stepped units now installed, on schedule, all four stands of the stadium are intact.

Gareth Jacques, Laing O’Rourke’s Project Director, said:

“Structurally, that is the stadium bowl complete.

“When you consider that alongside the terracing, the team have also done the structural steel and precast concrete in the four stands, it is a fantastic achievement.

“Because we use modern methods of construction and need to fix our design to go to fabrication early, the team worked really hard in the early stages of the project.

“The rate of progress we have achieved within the stadium meant that we were nearly 40% ready to go with precast components when we took possession of the site, so it’s been a great piece of work and a great product from our supply chain partner Banagher, in Ireland.”

Everton Stadium. Credit: Mark Seddon
Everton Stadium. Credit: Mark Seddon

The terrace units, averaging just under 9.5 tonnes in weight, have each been meticulously lifted into place over the past 18 months, secured with a high-strength grout and then made weatherproof with a special sealant.

And the installation of the bespoke, double-stepped units – ranging from 0.73m to 14m in length – is a first for Laing O’Rourke, who pivoted from more traditional single-stepped blocks due to a combination of factors.

Jacques said:

“The double-stepped units are something we haven’t done before. In previous stadiums we have built, it has been a single-step arrangement, but there are a few reasons for developing the new method here.

“One was that we were always aware of the exposed location of the site, and plenty of our engineered solutions have been done to reduce the risk of weather and lifting.

“The double-stepped terracing significantly reduces the amount of lifts needed and cuts down the time working on site, often at heights.

“The by-product is that when you are building a football stadium, all the internal works and fit-out are generally underneath the terracing, so getting weathertight is on the critical path.

“The infill joints are really important and here at Everton we have 33km of Mastic sealant within the bowl, so by having double-stepped units we need less of that too.”

For more info on Everton Stadium click here. For the latest news in Liverpool click here.

Share

Tags

The Guide Liverpool

About Us

We showcase the very best of Liverpool City Region through stunning video features and keep residents and visitors updated on what's on and what's good. About Us

The Guide Liverpool

Meet Our Team 👋

Meet Our Team
Eurovision 2023 - Jay And Gem - The Guide Liverpool Video Production

The Guide Liverpool

Video Production & Advertising

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse quis eros sit amet mi eleifend tincidunt. Services